| Line 166: |
Line 166: |
| | |process_rule_gazette_doc_issue=Α | | |process_rule_gazette_doc_issue=Α |
| | }} | | }} |
| | + | |
| | {{process steps | | {{process steps |
| | |process_step_num_id=1 | | |process_step_num_id=1 |
| | |process_step_exit=No | | |process_step_exit=No |
| | |process_step_child=No | | |process_step_child=No |
| − | |process_step_title=Submission of application and required documentation | + | |process_step_title=Start of procedure |
| − | |process_step_official=Other | + | |process_step_duration_min=0 |
| | + | |process_step_duration_max=0 |
| | + | }} |
| | + | |
| | + | {{process steps |
| | + | |process_step_num_id=2 |
| | + | |process_step_exit=No |
| | + | |process_step_child=Yes |
| | + | |process_step_previous_child_selector=1 |
| | + | |process_step_previous_child=1 |
| | + | |process_step_title=Submission of application |
| | + | |process_step_official=Competent directorate |
| | |process_step_implementation=Manual Action | | |process_step_implementation=Manual Action |
| | |process_step_duration_min=PT4H | | |process_step_duration_min=PT4H |
| | |process_step_duration_max=PT4H | | |process_step_duration_max=PT4H |
| − | |process_step_description=The interested party submits to the Protocol Office of the Directorate of Transport and Communications of the relevant Regional Unit an Application – Solemn Declaration announcing the operation of an IKTEO following a change of installation details, accompanied by all the required evidence. | + | |process_step_description=The interested party submits to the Registry Office of the Directorate of Transport and Communications of the relevant Regional Unit, or to the KEP operating as a Single Service Centre, the application-solemn declaration announcing the operation of an IKTEO following a change in installation details, accompanied by all supporting documents required in each case. |
| | + | |process_step_note=Joint Ministerial Decision 26640/2298/2014 (Government Gazette B’ 1302), Annex I, provides application templates. |
| | + | }} |
| | + | |
| | + | {{process steps |
| | + | |process_step_num_id=3 |
| | + | |process_step_exit=No |
| | + | |process_step_child=Yes |
| | + | |process_step_previous_child_selector=1 |
| | + | |process_step_previous_child=1 |
| | + | |process_step_title=Electronic submission of application and supporting documents |
| | + | |process_step_official=Software |
| | + | |process_step_implementation=Software action |
| | + | |process_step_duration_min=PT15M |
| | + | |process_step_duration_max=PT15M |
| | }} | | }} |
| | + | |
| | {{process steps | | {{process steps |
| − | |process_step_num_id=2 | + | |process_step_num_id=4 |
| | + | |process_step_exit=No |
| | + | |process_step_child=No |
| | + | |process_step_title=Registration of application |
| | + | |process_step_official=Competent directorate |
| | + | |process_step_implementation=Manual Action |
| | + | |process_step_duration_min=P2D |
| | + | |process_step_duration_max=P2D |
| | + | |process_step_description=The employee of the Registry Office of the Directorate of Transport and Communications of the Regional Unit receives and registers the application and forwards it to the competent Department. |
| | + | }} |
| | + | |
| | + | {{process steps |
| | + | |process_step_num_id=5 |
| | + | |process_step_exit=No |
| | + | |process_step_child=No |
| | + | |process_step_title=Completeness and correctness check |
| | + | |process_step_official=Competent department |
| | + | |process_step_implementation=Check |
| | + | |process_step_duration_min=P5D |
| | + | |process_step_duration_max=P5D |
| | + | |process_step_description=The employee of the Technical Department/competent Directorate checks the completeness and correctness of the supporting documents. |
| | + | If deficiencies are identified, the interested party is informed of the need to provide supplementary information. |
| | + | }} |
| | + | |
| | + | {{process steps |
| | + | |process_step_num_id=6 |
| | + | |process_step_exit=No |
| | + | |process_step_child=No |
| | + | |process_step_title=Informing the interested party of lack of requirements |
| | + | |process_step_official=Competent department |
| | + | |process_step_implementation=Manual Action |
| | + | |process_step_duration_min=P2D |
| | + | |process_step_duration_max=P2D |
| | + | |process_step_description=If the conditions for issuing the certificate of lawful operation are not met, the competent employee drafts and sends an information letter to the interested party. |
| | + | }} |
| | + | |
| | + | {{process steps |
| | + | |process_step_num_id=7 |
| | + | |process_step_exit=No |
| | + | |process_step_child=No |
| | + | |process_step_title=Forwarding of application for on-site inspection |
| | + | |process_step_official=Competent department |
| | + | |process_step_implementation=Manual Action |
| | + | |process_step_duration_min=P1D |
| | + | |process_step_duration_max=P1D |
| | + | |process_step_description=If the requirements are met and an on-site inspection is required, the application is forwarded to an inspection team to carry out the on-site inspection. |
| | + | }} |
| | + | |
| | + | {{process steps |
| | + | |process_step_num_id=8 |
| | |process_step_exit=No | | |process_step_exit=No |
| | |process_step_child=No | | |process_step_child=No |
| − | |process_step_title=On-site inspection | + | |process_step_title=On-site inspection - relevant report |
| | |process_step_official=Collective body | | |process_step_official=Collective body |
| − | |process_step_implementation=Inspection | + | |process_step_implementation=Check |
| | |process_step_duration_min=P5D | | |process_step_duration_min=P5D |
| | |process_step_duration_max=P5D | | |process_step_duration_max=P5D |
| − | |process_step_description=A team of experts performs an on-site inspection and prepares an Inspection Report. | + | |process_step_description=An on-site inspection is carried out by the inspection team and a relevant report is drawn up. |
| | }} | | }} |
| | + | |
| | {{process steps | | {{process steps |
| − | |process_step_num_id=3 | + | |process_step_num_id=9 |
| | |process_step_exit=Yes | | |process_step_exit=Yes |
| − | |process_step_child=No | + | |process_step_child=Yes |
| − | |process_step_title=Dispatch of attestation | + | |process_step_previous_child_selector=8 |
| − | |process_step_official=Competent Employee | + | |process_step_previous_child=8 |
| | + | |process_step_title=Rejection of application |
| | + | |process_step_official=Competent department |
| | + | |process_step_implementation=Manual Action |
| | + | |process_step_duration_min=P1D |
| | + | |process_step_duration_max=P1D |
| | + | |process_step_description=The report is received. In the event of rejection, the interested party is informed of the reasons for rejection. |
| | + | }} |
| | + | |
| | + | {{process steps |
| | + | |process_step_num_id=10 |
| | + | |process_step_exit=No |
| | + | |process_step_child=Yes |
| | + | |process_step_previous_child_selector=8 |
| | + | |process_step_previous_child=8 |
| | + | |process_step_title=Approval of application |
| | + | |process_step_official=Competent department |
| | |process_step_implementation=Manual Action | | |process_step_implementation=Manual Action |
| | |process_step_duration_min=P1D | | |process_step_duration_min=P1D |
| | |process_step_duration_max=P1D | | |process_step_duration_max=P1D |
| − | |process_step_description=The employee of the Technical Department / competent Directorate sends/ hands the attestation of lawful operation to the interested party and notifies it to the Directorates of Technical Inspections of Vehicles (DTEO) and Organisation and Information Technology (DOP) of the Ministry of Infrastructure and Transports, as well as to the local Police Authority and Fire Department. | + | |process_step_description=If the supporting documents are complete, and the on-site inspection report has been received or no on-site inspection was required, and provided that the operating requirements are met, a draft decision is prepared and forwarded for signature by the Head of the Technical Department. |
| | + | }} |
| | + | |
| | + | {{process steps |
| | + | |process_step_num_id=11 |
| | + | |process_step_exit=No |
| | + | |process_step_child=Yes |
| | + | |process_step_previous_child_selector=10 |
| | + | |process_step_previous_child=10 |
| | + | |process_step_title=Signing of certificate by the Head of the Technical Department |
| | + | |process_step_official=Competent Head of Department |
| | + | |process_step_implementation=Signature |
| | + | |process_step_duration_min=P3D |
| | + | |process_step_duration_max=P3D |
| | + | |process_step_description=The certificate of lawful operation is signed by the Head of the Technical Department. |
| | + | }} |
| | + | |
| | + | {{process steps |
| | + | |process_step_num_id=12 |
| | + | |process_step_exit=No |
| | + | |process_step_child=Yes |
| | + | |process_step_previous_child_selector=11 |
| | + | |process_step_previous_child=11 |
| | + | |process_step_title=Signing of certificate by the Head of the Directorate of Transport and Communications |
| | + | |process_step_official=Competent Director |
| | + | |process_step_implementation=Signature |
| | + | |process_step_duration_min=P3D |
| | + | |process_step_duration_max=P3D |
| | + | |process_step_description=The certificate of lawful operation is signed by the Head of the Directorate of Transport and Communications of the Regional Unit. |
| | + | }} |
| | + | |
| | + | {{process steps |
| | + | |process_step_num_id=13 |
| | + | |process_step_exit=No |
| | + | |process_step_child=Yes |
| | + | |process_step_previous_child_selector=12 |
| | + | |process_step_previous_child=12 |
| | + | |process_step_title=Signing of certificate by the Vice-Regional Governor or the Head of the Directorate of Transport and Communications of the Region |
| | + | |process_step_official=Regional Governor |
| | + | |process_step_implementation=Signature |
| | + | |process_step_duration_min=P3D |
| | + | |process_step_duration_max=P3D |
| | + | |process_step_description=The certificate of lawful operation is signed by the Vice-Regional Governor or the Head of the Directorate of Transport and Communications of the Region. |
| | + | }} |
| | + | |
| | + | {{process steps |
| | + | |process_step_num_id=14 |
| | + | |process_step_exit=Yes |
| | + | |process_step_child=Yes |
| | + | |process_step_previous_child_selector=13 |
| | + | |process_step_previous_child=13 |
| | + | |process_step_title=Delivery of certificate to the interested party - notification |
| | + | |process_step_official=Competent department |
| | + | |process_step_implementation=Manual Action |
| | + | |process_step_duration_min=P3D |
| | + | |process_step_duration_max=P3D |
| | + | |process_step_description=The employee of the Technical Department/competent Directorate sends/delivers the certificate of lawful operation to the interested party and communicates it to the Directorate of Supervision and Control (D36) and the IT and Electronic Systems Service (D9) of the Ministry of Infrastructure and Transport, as well as to the police authority and the fire service of the area. |
| | }} | | }} |