Issuance of an establishment licence for a dedicated or mixed CNG/CBG/BioCNG filling station

From National Registry of Administrative Public Services



238dbeb6-646b-4cae-aaf2-3b320dbdfc94 238664 Άδεια ίδρυσης αμιγούς ή μικτού Πρατήριου CNG/CBG/BioCNG

At a glance

Points of service

Points of Single Contact (ΚΕΠ – EKE), Regional units, At the Directorate of Transport & Communications of the relevant Regional Unit.

Digital provision points

Number of required documents

8 to 12

Fees

Variable

Deadline of completion

30 days

Description

This procedure concerns the granting of an establishment licence for a dedicated or mixed CNG/CBG/BioCNG filling station for public use to natural or legal persons, for the purpose of carrying out construction works.

Basic information

Competent body

MINISTRY OF INFRASTRUCTURE AND TRANSPORTATION

Authority/Public body’s Unit responsible for the institutional framework of the procedure

,

Service / organizational unit of a authority entity

At the Directorate of Transport & Communications of the relevant Regional Unit.

Validity duration

Variable subject to conditions

Notes

Joint Ministerial Decision (JMD) no. 11709/15-01-2024 (Government Gazette, Series B, No. 402) defines the terms, conditions, technical specifications, and the procedure for issuing establishment and operating licences for the installation and operation of dedicated or mixed filling stations—designed for the storage and distribution of compressed natural gas, biomethane, or a mixture of natural gas and biomethane (CNG/CBG/BioCNG)—for use by motor vehicles, whether for public or private use. Depending on the categories of fuel handled, a "CNG/CBG/BioCNG filling station" is classified as follows: i) A "dedicated CNG/CBG/BioCNG filling station"—whether for public or private use—which supplies motor vehicles exclusively with CNG/CBG/BioCNG. ii) A "mixed CNG/CBG/BioCNG filling station"—whether for public or private use—which supplies motor vehicles with CNG/CBG/BioCNG, liquid fuels (gasoline/diesel), and/or liquefied petroleum gas (LPG) (the latter only in the case of a public station), in any combination thereof.



The establishment licence is granted within thirty (30) working days, provided that the legal requirements are met. In the event that supporting documentation is resubmitted, the licence is granted within fifteen (15) working days, provided that the legal requirements are met.

For the purpose of carrying out construction work, the establishment licence is valid for a period of two (2) years; it may be extended for an additional two (2) years, provided that a relevant application is submitted prior to the expiration of the initial term, accompanied by a solemn declaration from the supervising engineer stating that the construction work has not yet been completed. In exceptional cases, an additional extension of three (3) months may be granted following the expiration of the extension period for the completion of the works.

Upon completion of the construction works, the establishment licence remains valid indefinitely, serving as the legal title for the existing facilities.

Last update

05/11/2026

Application

Application Type

Application

Submission by:

Submitted by the applicant (exclusively in person)

Submitted by:

Legal entities, Persons

Title

Application for the issuance of an establishment licence for a dedicated or mixed CNG/CBG/BioCNG filling station for public use.

Notes:

The application is submitted by the applicant (a natural or legal person). Otherwise, documents evidencing the authorization of the representative must be submitted along with the application.



In the event that the applicant is a legal person, the application—accompanied by the relevant supporting documentation—must be submitted by its legal representative. The application is submitted by the applicant to the competent Directorate of Transport and Communications of the relevant Regional Unit.

Alternatively, the interested party may submit the application, along with the required supporting documents, to a Citizen Service Centre (KEP-EKE); the latter shall then forward the application and the relevant file to the competent Directorate of Transport and Communications of the relevant Regional Unit.

What you will need

Means of authentication, identification and signature

Identification document

    Print

    Requirements

      Fees

        Means of redress or appeal:

        Administrative appeal, Other Administrative Appeal

        Provision is made for a request for administrative review (*aitisi therapeias*) to be submitted to the authority that issued the act, or for a special administrative appeal to be filed with the Coordinator of the Decentralized Administration within a 15-day deadline, in accordance with the provisions of Articles 227 and 228 of Law 3852/2010 (Government Gazette, Series A, No. 87), as amended by Law 4555/2018 (Government Gazette, Series A, No. 133) and currently in force.

        NACE

        • Retail sale of automotive fuel in specialised stores

        Output & Results

        Methods of receipt

        Other

        Output

        Decision, Administrative Act, Launch another procedure, Document Production

        Steps

          Digital steps

            Other information

            Alternative titles

            Establishment Licence for a dedicated or mixed CNG/CBG/BioCNG Filling Station for public use

            Official title

            Issuance of an Establishment Licence for a dedicated or mixed CNG/CBG/BioCNG Filling Station

            Languages supported

            Greek, English

            Ways of provision

            Establishment

            Registries updated

            ΜΗΤΡΩΟ ΠΡΑΤΗΡΙΩΝ ΠΑΡΟΧΗΣ ΚΑΥΣΙΜΩΝ ΚΑΙ ΕΝΕΡΓΕΙΑΣ

            Legislation

              Categories

              Τype of procedure

              Trigger

              Applied for

              Trigger (submission method)

              Application (handwritten)

              Type

              Outgoing

              End of Process

              Ιndefinite

              N1

              , ,


            • 1 Administrative In order for an establishment licence to be granted, the terms, conditions, technical specifications, and the issuance procedure stipulated in Joint Ministerial Decision (JMD) no. 11709/15-01-2024 (Government Gazette, Series B, No. 402) must be met.

              No No

            • 2 Of Spatial Planning The minimum safety distances for dedicated or mixed CNG/CBG/BioCNG filling stations must be observed (Article 5 of JMD no. 11709/15-01-2024).

              No No

            • 3 Citizenship In order to be granted a licence for the establishment of a filling station, natural persons—or members of companies—must be either Greek nationals or citizens of a Member State of the European Union or the European Economic Area (EEA). By way of exception, the granting of a licence to establish a liquid fuel filling station is permitted for ethnic Greeks (*omogeneis*) from Russia, Northern Epirus, Turkey, and Egypt, as well as for the children of such individuals.

              For *sociétés anonymes* (public limited companies) with their registered office in the country, the nationality of the shareholders is not taken into consideration (paragraph 4 of Article 185, Law 4070/2012).

              No No

            • 4 Establishment The legal entity must have its registered office in Greece.

              No No

            • 5 Age The interested party (the natural person, or—in the case of a legal entity—its members and its representative) must have reached the age of majority, in accordance with electoral legislation.

              No No

            • 6 Ownership The interested party—whether a natural person or a legal entity—must possess the right to use and exploit the plot of land or site for the purpose of establishing a fuel station.

              No No

            • 7 Judicial In the case of a natural person, the interested party must not have been subject to a final conviction for fuel adulteration within the last eight years, nor to a first-instance conviction for fuel smuggling, subject to the provisions of Law 4177/2013 (Government Gazette, Series A, No. 183).

              In the case of a legal entity: The legal representative must not have been subject to a final conviction, and the legal entity they represent must not have been held civilly liable (by a final judgment) for fuel adulteration within the last eight years. Furthermore, the legal representative must not have been subject to a first-instance conviction, and the legal entity they represent must not have been held civilly liable (by a first-instance judgment) for fuel smuggling, subject to the provisions of Law 4177/2013 (Government Gazette, Series A, No. 183).

              No No

            • 8 Urban planning The location where the filling station is to be established must be in an area permitted by the land-use regulations and the building terms and restrictions in force for that area, and where such use/installation is not prohibited by the applicable land-use provisions.

              No No

            • 9 Technical The design of the filling station’s facilities and equipment must take into account the requirements of current legislation, as well as relevant national and European regulations and standards.

              No No

            • 10 Administrative An application must have been submitted to the competent road authority for approval to lower the sidewalk curb (curb cut) or to establish a traffic connection, as the case may be.

              No No

            • 11 Environmental The facilities must be subject to the Standard Environmental Commitments.

              No No

            • 12 Time limit Construction work must be completed within two years, in accordance with the provisions of the applicable regulatory framework. (The establishment licence is valid for a period of two (2) years and may be extended for an additional two (2) years, provided that a relevant application is submitted before the expiration of the deadline, accompanied by a solemn declaration from the supervising engineer stating that construction works have not been completed.

              In exceptional cases, an additional extension of three (3) months may be granted following the expiration of the extension period for the completion of the works.

              No No

            • 13 Other For the establishment and operation of a mixed CNG/CBG/BioCNG filling station—which includes any type of fuel in addition to CNG/CBG/BioCNG—the terms and conditions for the establishment and operation of a liquid fuel station or a dedicated liquefied petroleum gas (LPG) station shall also be examined, as applicable.

              No No

            • 14 Of Spatial Planning Regarding the spatial siting, traffic connection (for areas outside the city plan), or curb cut/lowering of the sidewalk level (for areas within the city plan)—as applicable—for dedicated or mixed CNG/CBG/BioCNG filling stations undergoing the licensing process, the diagrams provided in Presidential Decree 1224/1981 (Government Gazette, Series A, No. 303) or Royal Decree 465/1970 (Government Gazette, Series A, No. 150) shall apply, as amended and currently in force.

              No No

            • 1 Issuance of the licence: €30. Additionally, for each pump or dispenser beyond the first (1st): €30. 0 €

              e-Administrative Fee code 8240

              Cost Calculation Quantitative

              Method of Payment Hellenic Post, Bank cashier, Digital (debit / credit card), Digital (web banking)

              Type of Cost e-Administrative Fee (variable)

              Fee Link https://www1.gsis.gr/sgsisapps/eparavolo/public/create.htm?langId=1

              No

            • 1 Residence permit Stay Permit

              Residence permit

              Submission by: Presented by the applicant

              Submitted by: Persons

              Notes: Ethnic Greeks from Turkey (*omogeneis*), upon submission of the required documentation, shall also present their valid residence document issued by the Aliens Centre, provided that the registration number of said document is recorded on the application.

              Document submitted under requirements: Yes

              Document’s requirement: Citizenship

              No 3465

            • 2 A topographical plan of the area (one copy), in accordance with paragraph 1(b) of Article 12 of the Joint Ministerial Decision (JMD) no. 11709/15-01-2024 (Government Gazette, Series B, No. 402). It must be signed by the competent engineer, drawn to a scale of 1:200 or 1:500, and cover a radius of fifty (50) meters from the boundaries of the plot or land parcel; the coordinates of the site must be referenced to the National Geodetic Reference System (EGSA 87). Topographical drawing

              A topographical plan of the area (one copy), in accordance with paragraph 1(b) of Article 12 of the Joint Ministerial Decision (JMD) no. 11709/15-01-2024 (Government Gazette, Series B, No. 402).

              It must be signed by the competent engineer, drawn to a scale of 1:200 or 1:500, and cover a radius of fifty (50) meters from the boundaries of the plot or land parcel; the coordinates of the site must be referenced to the National Geodetic Reference System (EGSA 87).

              Submission by: Submitted by the applicant (in person)

              Submitted by: Legal entities, Persons

              Notes: The diagram shall indicate the plot or land parcel intended for the proposed dedicated or mixed CNG/CBG/BioCNG filling station, the dimensions of its boundaries, its location in relation to road widths, and the positioning of the building, tanks or cylinders, pumps and dispensers, and the tank or cylinder filling point, as well as the types of neighboring structures. Specifically, the diagram must indicate the locations of the key components of the proposed dedicated or mixed CNG/CBG/BioCNG filling station, along with all safety distances required under Article 5 of the Joint Ministerial Decision (JMD) no. 11709/15-01-2024 (Government Gazette, Series B, No. 402).

              The drawings and technical reports must be signed by the competent engineer and include a legend detailing the project, the applicant, and the designer, as well as a section outlining the technical specifications of the construction. The drawings and technical reports shall also be submitted in electronic format (PDF files) on a portable storage device (USB flash drive).

              Document submitted under requirements: No


              No 6851

            • 3 Opinion from the Competent Authority, in accordance with paragraph 1(b) of Article 12 of Joint Ministerial Decision (JMD) no. 11709/15-01-2024 (Government Gazette, Series B, No. 402). Advisory

              Opinion from the Competent Authority, in accordance with paragraph 1(b) of Article 12 of Joint Ministerial Decision (JMD) no. 11709/15-01-2024 (Government Gazette, Series B, No. 402).

              Submission by: Submitted by the applicant (in person)

              Submitted by: Legal entities, Persons

              Notes: If the dedicated or mixed filling station is located in the vicinity of areas subject to special protective provisions for the environment, as well as for cultural and natural heritage (archaeological sites/monuments, Natura 2000 sites, etc.), the opinion of the competent authority is required.

              Document submitted under requirements: Yes

              Document’s requirement: Environmental, Of Spatial Planning

              No 5300

            • 4 A solemn declaration by the applicant, pursuant to Article 8 of Law 1599/1986, confirming the absence of a criminal conviction and the legal right to use and operate the plot of land, in accordance with point (c) of paragraph 1, Article 12 of the Joint Ministerial Decision (JMD) no. 11709/15-01-2024. Solemn Declaration

              A solemn declaration by the applicant, pursuant to Article 8 of Law 1599/1986, confirming the absence of a criminal conviction and the legal right to use and operate the plot of land, in accordance with point (c) of paragraph 1, Article 12 of the Joint Ministerial Decision (JMD) no. 11709/15-01-2024.

              Relevant link: https://www.gov.gr/ipiresies/polites-kai-kathemerinoteta/psephiaka-eggrapha-gov-gr/ekdose-upeuthunes-deloses

              Submission by: Submitted by the applicant (in person)

              Submitted by: Legal entities, Persons

              Relevant Procedure: Solemn declaration and electronic solemn declaration

              Notes: Specifically: a) In the event that the applicant is a natural person, they must solemnly declare that: i) within the last eight years, they have not been subject to a final (irrevocable) conviction for fuel adulteration, nor to a first-instance conviction for fuel smuggling, without prejudice to the provisions of Law 4177/2013 (Government Gazette, Series A, No. 183).

              ii) they possess the legal right to use and operate the plot of land or site for the establishment of the dedicated or mixed CNG/CBG/BioCNG filling station. b) In the event that the applicant is a legal entity, its legal representative shall provide a solemn declaration stating that:

              i) within the last eight years, neither the representative personally nor the legal entity they represent has been subject to a final conviction or a final judgment of civil joint liability for fuel adulteration; furthermore, neither the representative personally nor the legal entity they represent has been subject to a first-instance conviction or a first-instance judgment of civil joint liability for fuel smuggling—without prejudice to the provisions of Law 4177/2013 (Government Gazette, Series A, No. 183).

              ii) the legal entity holds the legal right to use and operate the plot of land or site for the establishment of a dedicated or mixed CNG/CBG/BioCNG filling station.

              Document submitted under requirements: No


              No 7320

            • 5 Solemn declaration (pursuant to Law 1599/86) by the engineer responsible for the design of the facility, in accordance with point (d) of paragraph 1, Article 12 of the Joint Ministerial Decision (JMD) no. 11709/15-01-2024. Solemn Declaration

              Solemn declaration (pursuant to Law 1599/86) by the engineer responsible for the design of the facility, in accordance with point (d) of paragraph 1, Article 12 of the Joint Ministerial Decision (JMD) no. 11709/15-01-2024.

              Relevant link: https://www.gov.gr/ipiresies/polites-kai-kathemerinoteta/psephiaka-eggrapha-gov-gr/ekdose-upeuthunes-deloses

              Submission by: Submitted by the applicant (in person)

              Submitted by: Legal entities, Persons

              Relevant Procedure: Solemn declaration and electronic solemn declaration

              Notes: A solemn declaration, pursuant to Article 8 of Law 1599/1986, by the engineer responsible for the design of the installation, stating the following: i) The location where the filling station is to be established lies within an area where such use is not prohibited by the applicable land-use regulations. ii) The terms and conditions of Joint Ministerial Decision (JMD) no. 11709/15-01-2024 (Government Gazette, Series B, No. 402) are met for a dedicated CNG/CBG/BioCNG filling station; in the case of a mixed filling station, the terms and conditions of Presidential Decree 1224/1981, Royal Decree 465/1970, and/or Presidential Decree 595/1984—as currently in force, depending on the specific fuel type—are also met. iii) The requirements of relevant national and European standards and regulations have been taken into account in the design of the installations and the equipment to be installed at the dedicated or mixed CNG/CBG/BioCNG filling station under development. iv) An application bearing reference no. ... has been submitted to the competent authority responsible for the maintenance and operation of the road(s) situated in front of the dedicated or mixed CNG/CBG/BioCNG filling station; the application meets all the requirements for the granting of approval for the lowering of the sidewalk curb, approval for an entrance/exit, or approval for a traffic connection, as the case may be.

              Document submitted under requirements: No


              No 7320

            • 6 A plan, in one (1) copy, at a scale of 1:200, in accordance with paragraph 1(e) of Article 12 of the Joint Ministerial Decision (JMD) no. 11709/15-01-2024 (Government Gazette, Series B, No. 402). Drawings / studies by an engineer / architect

              A plan, in one (1) copy, at a scale of 1:200, in accordance with paragraph 1(e) of Article 12 of the Joint Ministerial Decision (JMD) no. 11709/15-01-2024 (Government Gazette, Series B, No. 402).

              Submission by: Submitted by the applicant (in person)

              Submitted by: Legal entities, Persons

              Notes: The plan, at a scale of 1:200, shall show the location of the building and any auxiliary structures; the positioning of the CNG/CBG/BioCNG dispensing units to be installed, auxiliary equipment, and any portable CNG/CBG/BioCNG storage media (in the case of a "satellite" or "subsidiary" CNG/CBG/BioCNG station); the CNG/CBG/BioCNG tanks or cylinders; the "integrated unit"; the parking area for CNG/CBG/BioCNG tanker trucks; the flow-metering arrangement provided by the distribution company; the layout of the traffic connection or the curb cut/lowered sidewalk section(s) interfacing with the road(s); as well as the signage for the aforementioned elements.

              The plans and technical reports must be submitted signed by the competent engineer and shall include a legend containing project details, information regarding the applicant and the designer, as well as a section detailing the technical specifications of the construction. The plans and technical reports shall also be provided in electronic format (as PDF files) on a portable storage device (USB flash drive).

              Document submitted under requirements: No


              No 5768

            • 7 Electromechanical (E/M) installation plan, submitted in one (1) copy at an appropriate scale—depending on the size of the installation—accompanied by a file containing the Technical Specifications. This applies to installations located outside the buildings of a dedicated or mixed CNG/CBG/BioCNG filling station, in accordance with paragraph 1(f) of Article 12 of Joint Ministerial Decision (JMD) no. 11709/15-01-2024. Electromechanical drawing

              Electromechanical (E/M) installation plan, submitted in one (1) copy at an appropriate scale—depending on the size of the installation—accompanied by a file containing the Technical Specifications. This applies to installations located outside the buildings of a dedicated or mixed CNG/CBG/BioCNG filling station, in accordance with paragraph 1(f) of Article 12 of Joint Ministerial Decision (JMD) no. 11709/15-01-2024.

              Submission by: Submitted by the applicant (in person)

              Submitted by: Legal entities, Persons

              Notes: The plan must clearly depict—in a distinct manner that demonstrates their harmonious coexistence and simultaneous proper operation—the following installations:

              • water supply and sewage networks
              • compressed air systems
              • any liquid fuel piping (in the case of a mixed filling station with liquid fuel facilities)
              • LPG supply piping (in the case of a mixed filling station with LPG facilities)
              • CNG/CBG/BioCNG piping
              • piping for filling storage vessels
              • tanks for liquid fuels, LPG, and CNG/CBG/BioCNG (in the case of a mixed filling station)
              • and the filling station’s electrical systems (power circuits, low-voltage/signal circuits, lighting, and grounding). Additionally, the plan must include the layout of the filling station’s explosion-proof (hazardous) zones.

              All plans and technical reports must be signed by the competent engineer and include a legend containing details regarding the project, the applicant, and the designer, as well as a section detailing the technical specifications of the construction. The plans and technical reports must also be submitted in electronic format (as PDF files) on a portable storage device (USB flash drive).

              Document submitted under requirements: No


              No 5280

            • 8 Detailed drawings and technical specifications—in one (1) copy and at a scale of 1:50 or 1:20—of the facilities and equipment, in accordance with paragraph 1(ζ) of Article 12 of the Joint Ministerial Decision (JMD) no. 11709/15-01-2024. Drawings / studies by an engineer / architect

              Detailed drawings and technical specifications—in one (1) copy and at a scale of 1:50 or 1:20—of the facilities and equipment, in accordance with paragraph 1(ζ) of Article 12 of the Joint Ministerial Decision (JMD) no. 11709/15-01-2024.

              Submission by: Submitted by the applicant (in person)

              Submitted by: Legal entities, Persons

              Notes: Specifically, the drawings must depict the following: aa) Floor plan and cross-section, showing all structures of the filling station (or combined filling station), their precise dimensions, as well as the construction specifications for walls, floors, ceilings, and any existing partitions required by the building permit. bb) Drawings of portable CNG/CBG/BioCNG storage units (in the case of a "subsidiary CNG/CBG/BioCNG filling station") and/or drawings of liquid fuel tanks, in accordance with the provisions of Article 17 of Presidential Decree 1224/1981 (Government Gazette, Series A, No. 303) and Royal Decree 465/1970 (Government Gazette, Series A, No. 150) (for cases involving a combined filling station with liquid fuel facilities), and/or LPG tanks, in accordance with the provisions of Article 25 of the Presidential Decree 595/1984 (Government Gazette, Series A, No. 218) (for the case of a mixed-use filling station that includes LPG installations). gg) Detailed drawings and specifications for other CNG/CBG/BioCNG installations—in the case of a dedicated CNG/CBG/BioCNG station, or a station combining liquid fuels and LPG—(such as air compressors, lifting equipment, automatic car wash systems, sludge/sediment traps, etc.), in accordance with the applicable provisions of Presidential Decree 1224/1981 (Government Gazette, Series A, No. 303), Royal Decree 465/1970 (Government Gazette, Series A, No. 150), and/or Presidential Decree 595/1984.

              The drawings and technical reports must be submitted signed by the competent engineer and must include a legend containing information regarding the project, the applicant, and the designer, as well as a legend detailing the technical specifications of the construction. The drawings and technical reports must also be provided in electronic format (PDF files) on a portable storage device (USB flash drive).

              Document submitted under requirements: No


              No 5768

            • 9 Technical report on the electromechanical (E/M) installations, signed by the competent engineer, detailing the overall structure of the installation, in accordance with paragraph 1 of Article 12 of Joint Ministerial Decision (JMD) no. 11709/15-01-2024. Technical report

              Technical report on the electromechanical (E/M) installations, signed by the competent engineer, detailing the overall structure of the installation, in accordance with paragraph 1 of Article 12 of Joint Ministerial Decision (JMD) no. 11709/15-01-2024.

              Submission by: Submitted by the applicant (in person)

              Submitted by: Legal entities, Persons

              Notes: Technical report on the electromechanical installations (in one (1) copy), detailing the overall structure of the installation, the individual sub-installations, the equipment and machinery being installed, their technical specifications, their connection and operational methods, the national and European standards and regulations applied during their design and installation, and the study on the zoning of explosion-hazardous areas.

              The plans and technical reports must be submitted signed by the competent engineer and must include a legend containing information about the project, the applicant, and the designer, as well as a legend detailing the technical specifications of the construction.

              The plans and technical reports must also be provided in electronic format (PDF files) on a portable storage device (USB flash drive).

              Document submitted under requirements: No


              No 1068

            • 10 Form for inclusion under Standard Environmental Commitments. Environmental Compliance Receipt

              Form for inclusion under Standard Environmental Commitments.

              Submission by: Submitted by the applicant (in person)

              Submitted by: Legal entities, Persons

              Notes: Form for adherence to standard environmental commitments, in accordance with the provisions of Joint Ministerial Decision (JMD) no. 46537/09-08-2013 (Official Gazette, Series B, 2036), as currently in force.

              Document submitted under requirements: No


              No 9681

            • 11 Required studies and supporting documentation concerning the implementation of additional protective measures for the reduction of minimum safety distances, in accordance with Article 5 of Joint Ministerial Decision (JMD) no. 11709/15-01-2024. Technical study'

              Required studies and supporting documentation concerning the implementation of additional protective measures for the reduction of minimum safety distances, in accordance with Article 5 of Joint Ministerial Decision (JMD) no. 11709/15-01-2024.

              Submission by: Submitted by the applicant (in person)

              Submitted by: Legal entities, Persons

              Notes: The above items must be submitted in addition to any other required documentation, as stipulated by the applicable regulatory framework. Plans and technical reports must be signed by the competent engineer and include a legend containing details of the project, the applicant, and the designer, as well as a legend detailing the technical specifications of the construction. Plans and technical reports must also be provided in electronic format (PDF files) on a portable storage device (USB flash drive).

              Document submitted under requirements: Yes

              Document’s requirement: Technical

              No 1439

            • 12 Legal authorization documents for the legal representative. Legal documents from legal entities

              Legal authorization documents for the legal representative.

              Submission by: Submitted by the applicant (in person)

              Submitted by: Legal entities

              Notes: If the applicant is a legal entity, the articles of association (statutes) must be submitted, along with documentation regarding the appointment or authorization of the legal representative.

              Document submitted under requirements: Yes

              Document’s requirement: Company law

              No 9338

            • Royal decree 465 1970 150 Α

              Description Regarding the terms and conditions for the installation and operation of fuel pumps at filling stations located outside approved city or town plans—or, more generally, outside inhabited areas—and regarding the traffic connection of such facilities to public roads, as currently in force (as amended).

              Legal references https://api.et.gr/apiFEK/1/1970/150/pdf

            • Presidential Decree 1224 1981 303 Α

              Description Regarding the terms and conditions for the establishment and operation of liquid fuel filling stations located within approved city or town plans, approved settlements, or, more generally, inhabited areas, as currently in force (as amended).

              Legal references https://api.et.gr/apiFEK/1/1981/303/pdf

            • Presidential Decree 118 2006 119 Α

              Description Amendment of Royal Decree 465/1970 "Regarding the terms and conditions for the installation and operation of fuel pumps at filling stations located outside approved city or town plans—or, more generally, outside inhabited areas—and regarding the traffic connection of such facilities to public roads" (Government Gazette, Series A, No. 150) and of Presidential Decree

              1224/1981 "Regarding the terms and conditions for the establishment and operation of liquid fuel filling stations located within approved city or town plans, approved settlements, or, more generally, inhabited areas" (Government Gazette, Series A, No. 303), as amended by Presidential Decree 509/1984 (Government Gazette, Series A, No. 181), Presidential Decree 143/1989 “Amendment of provisions regarding the terms and conditions for the installation and operation of fuel pumps and the traffic connection of facilities with roads” (Government Gazette, Series A, No. 69), Presidential Decree

              401/1993 (Government Gazette, Series A, No. 170) and Presidential Decree 125/1992 (Government Gazette, Series A, No. 56) “amendment and supplementation of Presidential Decree 143/89 (Government Gazette, Series A, No. 69)” and the repeal of provisions of Presidential Decree 327/1992 (Government Gazette, Series A, No. 163)," as amended and currently in force.

              Legal references https://api.et.gr/apiFEK/1/2006/119/pdf

            • Law 14, 22, 25 4439 2016 222 Α

              Description Incorporation into Greek legislation of Directive 2014/94/EU of the European Parliament and of the Council of 22 October 2014 on the deployment of alternative fuels infrastructure; simplification of the licensing procedure and other provisions regarding fuel and energy supply stations; and other provisions, as amended and currently in force.

              Legal references https://api.et.gr/apiFEK/1/2016/222/pdf

            • Joint Ministerial Decision 81540/1445/Φ.4.2 2015 2984 Β

              Description Simplification and integration of the following procedures:

              • 1) Granting of establishment and operating licences of liquid fuel stations;
              • 2) Granting of establishment and operating licences of dedicated liquefied petroleum gas (LPG) stations;
              • 3) Granting of establishment and operating licences of compressed natural gas (CNG) distribution stations—falling under the remit of the Directorate for the Control of Vehicles and Facilities of the Ministry of Infrastructure, Transport and Networks—into the "Single Service Centres" (E.KE.) system, as amended and currently in force.

              Legal references https://api.et.gr/apiFEK/2/2015/2984/pdf

            • Joint Ministerial Decision οικ. 24541/409/Φ.4.2/2018 2018 1424 Β

              Description Amendment of Joint Ministerial Decision no. oik.81540/1445/Φ.4.2./31-12-2015 (Official Gazette, Series B, 2984), titled “Simplification and integration of the procedures for:

              • 1) Granting establishment and operating licences of liquid fuel filling stations.
              • 2) Granting establishment and operating licences of dedicated liquefied petroleum gas (LPG) filling stations.
              • 3) Granting establishment and operating licences of compressed natural gas (CNG) filling stations—falling under the remit of the Directorate for the Control of Vehicles and Facilities of the Ministry of Infrastructure, Transport and Networks—into the system of Single Service Centres (E.K.E.),” as currently amended and in force.

              Legal references https://api.et.gr/apiFEK/2/2018/1424/pdf

            • Joint Ministerial Decision Α.1176 2024 6827 Β

              Description Procedures, technical specifications, and terms and conditions for the installation of monitoring and electronic data transmission systems for inputs and outputs,

              • a) at the facilities of operators of fuel and energy retail stations;
              • b) at the facilities of holders of a retail trade licence—specifically, sellers of heating oil;
              • c) at the facilities specified in cases (ζζ), (ηη), (θθ), (ιι), (ιαια), (ιβιβ), and (ιγιγ) of paragraph 7a of Article 31 of Law 3784/2009 (Government Gazette, Series A, No. 137). Compliance requirements, access to data by services, implementation timeline, transitional provisions, and any other necessary details regarding the safeguarding of data within the input-output monitoring system," as amended and currently in force.

              Legal references https://api.et.gr/apiFEK/2/2024/6827/pdf

            • Joint Ministerial Decision 46537 2013 2036 Β

              Description Establishment of Standard Environmental Commitments for Category B activities under Group 11, "Refilling stations for vehicles using gaseous or liquid fuels"—falling within the subgroup "transport and handling of fuels and chemical substances"—as currently in force.

              Legal references https://api.et.gr/apiFEK/2/2013/2036/pdf

            • Law 4 2801 2000 46 Α

              Description Regulations concerning matters under the jurisdiction of the Ministry of Transport and Communications, along with other provisions, as currently in force.

              Legal references https://api.et.gr/apiFEK/1/2000/46/pdf

            • Law 11 3897 2010 208 Α

              Description Establishment of a National Road Safety Council and a General Directorate for Road Safety; supervision and enhancement of the vehicle technical inspection system to promote road safety and environmental protection; ratification of an agreement between the Hellenic State and OASTH (Thessaloniki Urban Transport Organisation); and other provisions, as currently in force.

              Legal references https://api.et.gr/apiFEK/1/2010/208/pdf

            • Joint Ministerial Decision Α1093 2025 3654 Β

              Description Amendment of Joint Decision A.1176/5-12-2024 regarding “Procedures, technical specifications and terms and conditions for the installation of monitoring and electronic transmission systems for input-output data:

              • (a) at the facilities of operators of fuel and energy supply stations
              • b) the facilities of holders of a retail trade licence—specifically sellers of heating oil;
              • c) the facilities specified in cases (zz), (hh), (thth), (ii), (iaia), (ibib), and (igig) of paragraph 7a of Article 31 of Law 3784/2009 (Government Gazette, Series A, No. 137). compliance requirements, access to data by the relevant authorities, the implementation timeline, transitional provisions, and any other necessary details regarding the safeguarding of data within the input-output monitoring system” (Government Gazette, Series B, No. 6827).

              Legal references https://api.et.gr/apiFEK/2/2025/3654/pdf

            • Joint Ministerial Decision 11709 2024 402 Β

              Description Determination of technical specifications, competent authorities, and the terms and conditions for the establishment and operation of filling stations equipped with dispensing devices (refuelling points) for compressed natural gas (CNG), compressed biomethane, and a compressed mixture of natural gas and biomethane for motor vehicles, namely:

              • 1. stations exclusively for compressed natural gas (CNG), or
              • 2. mixed filling stations comprising a. liquid fuels, liquefied petroleum gas (LPG), and compressed natural gas (CNG), or b. liquefied petroleum gas (LPG) and compressed natural gas (CNG), or c. liquid fuels and compressed natural gas (CNG).

              Legal references https://api.et.gr/apiFEK/2/2024/402/pdf

            • Presidential Decree 595 1984 218 Α

              Description Terms and conditions for the installation and operation of LPG filling stations, as currently in force (as amended).

              Legal references https://api.et.gr/apiFEK/1/1984/218/pdf

            • 1 Initiation of the procedure



              No No


            • 2 Receipt of the application by the Transport Directorate of the relevant Regional Unit

              Responsible for Implementation Competent Public Agency

              Μethod of Implementation Manual Action

              Description The interested party submits an application for the establishment of a filling station to the Transport and Communications Directorate of the relevant Regional Unit, accompanied by all required supporting documents.

              Yes No


            • 3 Receipt of the application by a KEP-EKE (Citizen Service Centre – Single Point of Contact)

              Responsible for Implementation KEP (ΚΕΠ) employee

              Μethod of Implementation Manual Action

              Description The interested party submits the application, along with the required supporting documents, to a KEP-EKE; the latter then forwards the application and the relevant file to the competent Transport and Communications Directorate of the relevant Regional Unit.

              Yes No


            • 4 Forwarding of the application by a KEP-EKE

              Responsible for Implementation KEP (ΚΕΠ) employee


              Description The KEP-EKE forwards the application and the relevant file to the competent Transport and Communications Directorate of the relevant Regional Unit.

              Yes No


            • 5 Registration of the application

              Responsible for Implementation Competent Public Agency

              Μethod of Implementation Manual Action

              Description The application is assigned a registration number at the Directorate of Transport and Communications of the relevant Regional Unit.

              No No


            • 6 Review of the application

              Responsible for Implementation Competent Directorate

              Μethod of Implementation Inspection

              Description The Directorate of Transport and Communications of the relevant Regional Unit reviews the submitted application and the accompanying supporting documents.

              No No


            • 7 Completeness of the application

              Responsible for Implementation Competent Directorate

              Μethod of Implementation Inspection

              Description The legal requirements for granting the requested licence for the establishment of a filling station are met.

              Yes No


            • 8 Rejection of the application

              Responsible for Implementation Competent Directorate

              Μethod of Implementation Manual Action

              Description If the legal requirements are not met, the requested licence is not granted, and the applicant is notified in writing, with the relevant reasons stated.

              Yes Yes


            • 9 Document for resubmission

              Responsible for Implementation Competent Directorate

              Μethod of Implementation Manual Action

              Description The authority notifies the applicant in writing of the need to resubmit certain elements of their application.

              Yes No


            • 10 Re-examination of the application

              Responsible for Implementation Competent Directorate

              Μethod of Implementation Inspection

              Description The application is re-examined once the applicant has submitted the information requested by the Directorate of Transport and Communications of the relevant Regional Unit.

              Yes No


            • 11 Completeness of the application

              Responsible for Implementation Competent Directorate

              Μethod of Implementation Inspection

              Description The legal requirements for granting the requested licence for the establishment of a filling station are met.

              Yes No


            • 12 Rejection of the application

              Responsible for Implementation Competent Directorate

              Μethod of Implementation Manual Action

              Description If the legal requirements are not met, the requested licence shall not be granted, and the applicant shall be notified in writing, stating the relevant reasons.

              Yes Yes


            • 13 Issuance of an establishment licence

              Responsible for Implementation Competent Directorate

              Μethod of Implementation Manual Action

              Description If the legal requirements are met, the requested licence shall be issued.

              No No


            • 14 Notification of the establishment licence

              Responsible for Implementation Competent Directorate

              Μethod of Implementation Manual Action

              Description The establishment licence shall be notified to the applicant against a receipt of delivery.

              No No